Harbor Street repaving

Under construction, expected to finish January 2027

  1. Planned (done)
  2. Design (done)
  3. Bidding (done)
  4. Construction
  5. Complete

Milling and repaving Harbor Street from 1st to 5th Avenue, with new crosswalks and curb ramps at every corner.

Closures and detours now

  • Lane closedUntil Nov 23

    Harbor Street between 2nd and 3rd Avenue

    One lane each way. Expect short delays.

  • Road closedUntil Nov 22

    Harbor Street at 4th Avenue (intersection)

    Closed overnight for paving. Use Bay Avenue.

Type
Roads and streets
Where
Harbor Street from 1st Avenue to 5th Avenue
Construction starts
October 2026
Expected to finish
January 2027
Budget
$1.2 million
Paid for by
Local option gas tax and the half-cent sales tax
Contractor
Gulf Coast Paving
Questions
Public Works, (850) 555-0140

The street was last paved in 2004. Crews work one block at a time, 7 a.m. to 5 p.m. on weekdays, and keep one lane open in each direction except where noted below.

Businesses stay open during the work. Use the side streets to reach their parking lots.

Updates

  • Paving between 1st and 2nd Avenue is done. Crews move to the next block on Monday.

  • Work started. Expect lane closures on weekdays.

Where

Map data © OpenStreetMap contributors